Road Projects - Landsdale - Mirrabooka Avenue dual carriageway from Hepburn Avenue to Gnangara Road

Location
Suburb Landsdale
Ward South Ward
Key Facts
  • Construction of the second lane for the dual carriageway from Hepburn Avenue to Gnangara Road, Landsdale.
  • 2.6km length.
Completed Stages

Detailed design works

Current Stage

Service relocations and preparation for tendering construction works.

Upcoming Stages

Tendering and then construction by contract to commence in early 2018.

Expected Date of Completion Latter half of 2018
Enquiries

Ph: 9405 5000