Menu
Language
Home

Community Facility Projects - Wanneroo - City of Wanneroo Civic Centre extension

Location
Suburb Wanneroo
Ward Central Ward
Key Facts
  • New extension to City of Wanneroo Civic Centre building
  • Fitout and refurbishment of new building and existing Civic Centre building
Related Documents
Completed Stages

Civic centre extension building construction by PINDAN commenced 20 June 2016, and was completed 8th September 2017.

Current Stage

Fitout of new extension building and refurbishment existing civic centre building by BROAD CONSTRUCTION commenced 9th October 2017 and completed 24th November 2017. 

Upcoming Stages

Completion of fitout and refurbishment of Civic Centre 5th May 2018.

Expected Date of Completion 5 May 2018
Enquiries

Ph: 9405 5000
Email: enquiries@wanneroo.wa.gov.au

Page last updated: 5 April 2018

Project image