Community Facility Projects - Merriwa - Addison Park floodlight upgrade and oval extension

Location
Suburb Merriwa
Ward North
Key Facts

Extend the existing active open space to accommodate a senior size oval and upgrade the sports floodlighting. The proposed works will be designed in 2017/2018 and construction will occur in 2018/2019.

The extended oval will utilise additional park space and upgrading the floodlights means that the facility is available for club use for longer periods during the winter months.

Completed Stages

Concept design for the oval extension is complete. Floodlighting tender award recommended.

Current Stage

On Hold

Upcoming Stages
  • Tender
  • Contract award
  • Construction
  • Handover
Expected Date of Completion June 2019
Enquiries

Ph: 9405 5000
Email: enquiries@wanneroo.wa.gov.au

Date Last Updated: 18 February 2019.