Community Facility Projects - Madeley - Kingsway netball changeroom upgrades

Location
Suburb Madeley
Ward South Ward
Key Facts

The Kingsway Regional Sporting Complex Netball Clubrooms was a purpose built club house and change room constructed in 1974. 

Various alterations and additions have since been made to the building for the Wanneroo Districts Netball Association (WDNA), however, the continued expansion of the WDNA competition has seen the building struggle to support existing needs.

The Kingsway Netball Changerooms Upgrade comprises refurbishment of the existing WDNA offices, hall, kitchen, toilet amenities and changing rooms.  New building extensions incorporating additional space for WDNA offices aswell as new changing rooms, toilets and first aid room will also be constructed.

The City is investing $2.6 million towards the project which has a total budget of $3.1 million. Other financial contributions include a $500,000 grant from the Department of Local Government, Sports and Cultural Industries.

Completed Stages

Wangara based Geared Construction commenced construction in March 2019.

Stage 1 works included relocation of WDNA staff into a temporary office located on site and within the existing hall, to allow construction works to commence surrounding them. These works were completed 26th July 2019 and included construction of:

  • New kitchenette
  • First-aid room
  • Umpire and match official rooms
  • Toilets
  • New administration offices
  • Meeting rooms 

Following completion of Stage 1; the WDNA staff were then relocated to occupy on site their new administration offices whilst the Stage 2 construction works were completed.  This comprised of

  • New change rooms
  • Commercial kitchen and store rooms
  • Toilets
  • Refurbishment of the multi-purpose hall
  • Landscaping 

Stage 2 works were completed 24th January 2020, three months ahead of the original scheduled project completion date of 12th April 2020.

Current Stage

Defects liability period

Upcoming Stages

Project closeout.

Expected Date of Completion January 2020
Enquiries

Ph: 9405 5000
Email: enquiries@wanneroo.wa.gov.au

Page last updated: 20 April 2020.