Community Facility Projects - Neerabup - Neerabup Industrial Area - Upgrade Roads & Services

Location
Suburb Neerabup
Ward Central Ward
Key Facts

New water and wastewater services, upgrade drainage and roads, lighting, parking and paths to Neerabup Industrial Area.

Completed Stages
  • Stage 1a - Sewer extension through Wallangarra Reserve, Banksia Grove (June 2018).
  • Stage 1b - Water and sewer mains extension along Mather Dr, Warman St, Avery St and Turnbull Rd Mather Drive (July 2019).
Current Stage

Stage 2 & 3 (Remainder of works) Design development for road, pathways and landscaping.

Upcoming Stages
  • Stage 2 Construction (2020/21).
  • Stage 3 Construction (2021/22).
Expected Date of Completion June 2022
Enquiries

Ph: 9405 5000
Email: enquiries@wanneroo.wa.gov.au

Date Last Updated: 20 April 2020.