Road Projects - Wanneroo - Civic Drive asphalt renewal Dundebar Road to Celestine Street

Location
Suburb Wanneroo
Ward Central
Key Facts

Asphalt was replaced along Civic Drive for approximately 1km between Dundebar Road and Celestine Street. 

Works are due to extensive asphalt cracking and slumps appearing on this road, and will include replacement of kerbing and property crossovers as required.

Completed Stages

All works completed in December 2021.

Current Stage

Project complete

Expected Date of Completion

December 2021

Enquiries

Ph: 9405 5000
Email: enquiries@wanneroo.wa.gov.au

Date Updated: 1 March 2022