Neerabup Industrial Area Development Project
Project overview
The development of the Neerabup Industrial Area (NIA) has been a key strategic priority for the City of Wanneroo for a number of years. The City and state government own a majority of the developable land in the NIA, which will provide economic growth opportunities and local employment.
The City of Wanneroo Council at its Ordinary Council Meeting on 18 August 2015 noted the recommendations contained within the Order of Magnitude Business Plan and agreed to proceed with the development of the City of Wanneroo’s landholdings within the Neerabup Industrial Area, namely Lot 9000 (now Lot 9100), Lot 9003 and Lot 600.
Lot 9003 contains sand and limestone resources that require extraction in order to lower the ground levels to match the contour levels required under Structure Plan No. 17 Amendment 4. It will take approximately 15 years, over 5 stages to fully extract the resources and reduce the ground to the required levels. Land release will commence for industrial subdivision development following the completion of each stage.
The City of Wanneroo has engaged Urban Resources Pty Ltd to carry out its extractions works within the industrial area.
Lot 9100 Mather Drive, Neerabup – Subdivision Works
The City is undertaking the development of Lot 9100 Mather Drive within the Neerabup Industrial Area, as part of its long-term land development and investment program.
This development will support the continued growth of the Neerabup Industrial Area by providing additional land for businesses growth, local employment and strengthening the City’s economic development.
Lot 9100 will provide 41 serviced industrial lots. This project will deliver:
• new roads, retaining walls and footpaths
• stormwater drainage
• street lighting
• essential services including water, sewer, power, gas and telecommunications.
Construction is planned to commence in September 2026, with completion planned within 12 months.
Subscribe to Neerabup Industrial Area updates
Location
Project news
Project timeline
| Planning and approval | |
| Development approvals achieved TBC | |
| Detailed design | |
| TBC | |
| Construction phase | |
| September/ October 2026 | |
| Expected completion | |
| End of 2027 | |
Funding
City of Wanneroo funded development.
Key documents
Construction Environmental Management Plan
Conservation Area Management Plan
Meridian Business Park - Compliance Report 2025-2026
Meridian Business Park - Compliance Report 2024-2025
Meridian Business Park - Compliance Report 2023-2024
Meridian Business Park - Compliance Report 2021-2022
Project contact
Name: Paul Greer, Manager Property Services
Phone: (08) 9405 5022