Road Projects - Road Resurfacing Program

Suburb Various suburbs
Ward Various
Key Facts

The 2022/23 Financial Year program of works includes the installation of:

  • Over 50,000m² of asphalt.
  • Over 2km of kerbing.
  • Approximately 500m² of concrete driveway.
  • Crossover and pathway reinstatements.

Locations

Carramar - October to December 2022

  • Balladong Loop
  • Bushland Retreat

Gnangara - October to December 2022

  • Sydney Road

Girrawheen - July to September 2022

  • Blackmore Avenue
  • Bus stop 16245
  • Kelly Road

Landsdale - October to December 2022

  • Cowle Street
  • Mosey Street

Marangaroo - October to December 2022

  • Giralt Road
  • Jefferson Drive
  • Rawlinson Drive

Quinns Rocks

  • Nicholas Avenue - July to September 2022
  • Quinns Rocks foreshore path (Clarecastle Retreat to Quinns SLSC) - April to June 2023

Wanneroo - October to December 2022

  • Ashby Street
  • Badgerup Road
  • Benmuni Road
  • Franklin Road
  • Garden Park Drive
  • Nicholas Road
  • Rousset Road
Current Stage

Girrawheen

  • Blackmore Avenue
  • Kelly Road
Upcoming Stages

To be confirmed.

Expected Date of Completion

June 2023.

Enquiries

Ph: 9405 5000
Email: enquiries@wanneroo.wa.gov.au

Page last updated: August 2022