Road Projects - Landsdale - Alexander Drive - New shared pathway

Project description

A new shared path will be installed on the west side of Alexander Drive from Gnangara Road to Hepburn Avenue. 

The 2.8km dual use red asphalt pathway will be installed to provide a safe and accessible pathway network for the community. 

In preparation for this project, works commenced in October 2024 to adjust the utilities services by removing power poles and undergrounding existing overhead power lines and lowering existing underground water, electrical, gas and telecommunication services along Alexander Drive.  As these works have progressed significantly, this has enabled construction of the new pathway to commence in stages. 

Stage 1 of the pathway construction, from Hepburn Avenue to Kingsway, will commence 12 May 2025 with anticipated completion by 27 June 2025. 

Details for further stages of construction will be provided in due course.

Partial road closure

  • To ensure safety for road users and pedestrians, the majority of construction works will take place under a one lane northbound closure on Alexander Drive. 
  • Access on Alexander Drive will be continuous throughout these works, with exception to the period of full road closure between 18 and 20 June 2025 as detailed below.
  • Temporary traffic management will be implemented to safely manage traffic and pedestrians around the worksite.
  • Whilst is it inevitable that works of this nature will cause some inconvenience, every endeavour will be made to ensure this is kept to a minimum.

Full road closure

  • Proposed for 18 to 20 June 2025 between the hours of 6pm and 4am.
  • Intersection at Kingsway and Alexander Drive will be closed to the public during the above dates and times.
  • Variable Message Boards will remain on verges to communicate road closures / night works to commuters and will include updates in response to changes that may occur during these works. 
  • Road detours will be in place which will, at times, result in increased traffic in the surrounding areas. 

Access to properties in the surrounding area will not be interrupted during these works and access to Kingsway and Alexander Drive will be available during the day.

Temporary traffic management will be implemented to safely manage traffic and pedestrians around the worksite. Whilst is it inevitable that works of this nature will cause some inconvenience, every endeavour will be made to ensure this is kept to a minimum.

Expected Date of Completion

2025 to 2026 financial year.

Status

Construction.

Location

Alexander Drive - between Hepburn Avenue and Gnangara Road.

Map
Upcoming Stages

Construction