Community engagement has now closed. Comments were submitted from 21/08/2017 to 15/09/2017.

At the 10 October 2017 City of Wanneroo Council meeting, the following recommendations were approved:

That Council:-

1.         ENDORSES the Edgar Griffiths Park Sports Amenities Building, Floodlighting, Oval Realignment Concept Plan as shown in Attachment 2 of this report;

2.         NOTES that construction of the proposed development is estimated to commence by end October 2017 and will be concluded in February 2019;

3.         ENDORSES the revised schedule of works for the Edgar Griffiths Park projects, to be undertaken within the 2017/18 and 2018/19 financial years as outlined within the table below;


Year

Project No.

Description

Total

1 (2017/18)

4101

Oval Extension and Sports Floodlighting - Design

69,000

1 (2017/18)

4101

Oval Extension and Sports Floodlighting – Construction

500,000

1 (2017/18)

4010

Sports Amenities Building - Detailed Design

50,000

 

 

Year 1 Total

619,000

2 (2018/19)

4106

Water Main Extension

150,000

2 (2018/19)

4010

Sports Amenities Building (New / Refurbishments / Additions) - Construct

1,650,000

 

 

Year 2

1,800,000

 

 

Project Total

2,419,000


4.         APPROVES BY ABSOLUTE MAJORITY the following budget amendment,  pursuant to Section 6.8(1)(b) of the Local Government Act 1995 to fund the delivery of PR-4101 Oval Extension and Sports Floodlighting – Construction in the 2017/18 financial year:


Project Number

From

To

Description

PR-4010

$350,000

 

Sports Amenities Building (New / Refurbishments / Additions) - Detailed Design & Construct Stage 1 (ARMP)

PR-4106

$150,000

 

Water Main Extension

PR-4101

 

$500,000

Oval Extension and Sports Floodlighting – Construction


5.         NOTES that as a part of the 2018/19 Budget development process,  item PR-4101 Oval Extension and Sports Floodlighting Construction ($687,000) will need to be brought forward from 2019/20 to 2018/19 and re-allocated to PR-4106 Water Main Extension and PR-4010 Sports Amenities Building Construction to enable the completion of the project in the 2018/19 financial year; and


6.         RECOGNISES and THANKS the community for its involvement in the community consultation component of the project


Information

The 2017/18 capital works budget has set aside funding to improve the current amenities at Edgar Griffiths Park which will benefit local sporting clubs, community members and support the existing use. Those improvements include;

1. A new sports amenities building
2. SMS controlled floodlighting
3. A minor upgrade to the oval alignment
4. Connection to scheme water

To ensure the proposed plans meet the community needs, the City invites you to view these plans and partake in this survey

Full plans are available on the City's Website at Community Facility Projects.

There will also be an onsite community BBQ at Edgar Griffiths Park, Wanneroo on Monday 11 September 2017 at 5:00pm where you can discuss your comments with Elected Members and City Staff.

Key Dates

  • Onsite Consultation
  • There will also be an onsite community BBQ at Edgar Griffiths Park, Wanneroo on Monday 11 September 2017 at 5:00pm where you can discuss your comments with Elected Members and City Staff.
  • Date: 11/09/2017
  • Time: 5pm
  • Location: Edgar Griffiths Park, Garden Park Drive, Wanneroo

Get Involved

Enquiries